85-2-343. Basin closure -- exceptions. (1) As provided in 85-2-319 and subject to the provisions of subsection (2) of this section, the department may not process or grant an application for a permit to appropriate water or for a reservation to reserve water within the upper Missouri River basin during the period from April 16, 1993, until the final decrees have been issued in accordance with part 2 of this chapter for all of the subbasins of the upper Missouri River basin.
(2) The provisions of subsection (1) do not apply to:
(a) an application for a permit to appropriate ground water;
(b) an application for a permit to appropriate water for a nonconsumptive use;
(c) an application for a permit to appropriate water for domestic, municipal, or stock use;
(d) an application to store water during high spring flows; or
(e) temporary emergency appropriations as provided for in 85-2-113(3).
History: En. Sec. 2, Ch. 385, L. 1993; amd. Sec. 455, Ch. 418, L. 1995.