     69-8-103. Definitions. As used in this chapter, unless the context requires otherwise, the following definitions apply:
     (1) "Aggregator" or "market aggregator" means an entity, licensed by the commission, that aggregates retail customers and purchases electric energy and takes title to electric energy as an intermediary for sale to retail customers.
     (2) "Assignee" means any entity, including a corporation, partnership, board, trust, or financing vehicle, to which a utility assigns, sells, or transfers, other than as security, all or a portion of the utility's interest in or right to transition property. The term also includes an entity, corporation, public authority, partnership, trust, or financing vehicle to which an assignee assigns, sells, or transfers, other than as security, the assignee's interest in or right to transition property.
     (3) "Board" means the board of investments created by 2-15-1808.
     (4) "Broker" or "marketer" means an entity, licensed by the commission, that acts as an agent or intermediary in the sale and purchase of electric energy but that does not take title to electric energy.
     (5) "Cooperative utility" means:
     (a) a utility qualifying as an electric cooperative pursuant to Title 35, chapter 18; or
     (b) an existing municipal electric utility as of May 2, 1997.
     (6) "Customer" or "consumer" means a retail electric customer or consumer. The university of Montana, pursuant to 20-25-201(1), and Montana state university, pursuant to 20-25-201(2), are each considered a single retail electric customer or consumer with a single individual load.
     (7) "Distribution facilities" means those facilities by and through which electricity is received from a transmission services provider and distributed to the customer and that are controlled or operated by a distribution services provider.
     (8) "Distribution services provider" means a person controlling or operating distribution facilities for distribution of electricity to the public.
     (9) "Electricity supplier" means any person, including aggregators, market aggregators, brokers, and marketers, offering to sell electricity to retail customers in the state of Montana.
     (10) "Financing order" means an order of the commission adopted in accordance with 69-8-503 that authorizes the imposition and collection of fixed transition amounts and the issuance of transition bonds.
     (11) (a) "Fixed transition amounts" means those nonbypassable rates or charges, including but not limited to:
     (i) distribution;
     (ii) connection;
     (iii) disconnection; and
     (iv) termination rates and charges that are authorized by the commission in a financing order to permit recovery of transition costs and the costs of recovering, reimbursing, financing, or refinancing the transition costs and acquiring transition property through a plan approved by the commission in the financing order, including the costs of issuing, servicing, and retiring transition bonds.
     (b) If requested by the utility in the utility's application for a financing order, fixed transition amounts must include nonbypassable rates or charges to recover federal and state taxes in which the transition cost recovery period is modified by the transactions approved in the financing order.
     (12) "Functionally separate" means a utility's separation of the utility's electricity supply, transmission, distribution, and unregulated retail energy services assets and operations.
     (13) "Local governing body" means a local board of trustees of a rural electric cooperative.
     (14) "Low-income customer" means those energy consumer households and families with incomes at or below industry-recognized levels that qualify those consumers for low-income energy-related assistance.
     (15) "Nonbypassable rates or charges" means rates or charges approved by the commission imposed on a customer to pay the customer's share of transition costs or universal system benefits program costs even if the customer has physically bypassed either the utility's transmission or distribution facilities.
     (16) "Pilot program" means a program using a representative sample of residential and small commercial customers to assist in developing and offering customer choice of electric supply for all residential and commercial customers.
     (17) "Public utility" means any electric utility regulated by the commission pursuant to Title 69, chapter 3, on May 2, 1997, including the public utility's successors or assignees.
     (18) "Transition bondholder" means a holder of transition bonds including trustees, collateral agents, and other entities acting for the benefit of that holder.
     (19) "Transition bonds" means any bond, debenture, note, interim certificate, collateral, trust certificate, or other evidence of indebtedness or ownership issued by the board or other transition bonds issuer that is secured by or payable from fixed transition amounts or transition property. Proceeds from transition bonds must be used to recover, reimburse, finance, or refinance transition costs and to acquire transition property.
     (20) "Transition charge" means a nonbypassable rate or charge to be imposed on a customer to pay the customer's share of transition costs.
     (21) "Transition cost recovery period" means the period beginning on July 1, 1998, and ending when a utility customer does not have any liability for payment of transition costs.
     (22) "Transition costs" means:
     (a) a public utility's net verifiable generation-related and electricity supply costs, including costs of capital, that become unrecoverable as a result of the implementation of this chapter or of federal law requiring retail open access or customer choice;
     (b) those costs that include but are not limited to:
     (i) regulatory assets and deferred charges that exist because of current regulatory practices and can be accounted for up to the effective date of the commission's final order regarding a public utility's transition plan and conservation investments made prior to universal system benefits charge implementation;
     (ii) nonutility and utility power purchase contracts, including qualifying facility contracts;
     (iii) existing generation investments and supply commitments or other obligations incurred before May 2, 1997, and costs arising from these investments and commitments;
     (iv) the costs associated with renegotiation or buyout of the existing nonutility and utility power purchase contracts, including qualifying facilities and all costs, expenses, and reasonable fees related to issuing transition bonds; and
     (v) the costs of refinancing and retiring of debt or equity capital of the public utility and associated federal and state tax liabilities or other utility costs for which the use of transition bonds would benefit customers.
     (23) "Transition period" means the period beginning on July 1, 1998, and ending on July 1, 2002, unless otherwise extended pursuant to this chapter, during which utilities may phase in customer choice of electricity supplier.
     (24) "Transition property" means the property right created by a financing order including without limitation the right, title, and interest of a utility, assignee, or other issuer of transition bonds to all revenue, collections, claims, payments, money, or proceeds of or arising from or constituting fixed transition amounts that are the subject of a financing order including those nonbypassable rates and other charges and fixed transition amounts that are authorized by the commission in the financing order to recover transition costs and the costs of recovering, reimbursing, financing, or refinancing the transition costs and acquiring transition property including the costs of issuing, servicing, and retiring transition bonds. Any right that a utility has in the transition property before the utility's sale or transfer or any other right created under this section or created in the financing order and assignable under this chapter or assignable pursuant to a financing order is only a contract right.
     (25) "Transmission facilities" means those facilities that are used to provide transmission services as determined by the federal energy regulatory commission and the commission.
     (26) "Transmission services provider" means a person controlling or operating transmission facilities.
     (27) "Universal system benefits charge" means a nonbypassable rate or charge to be imposed on a customer to pay the customer's share of universal system benefits program costs.
     (28) "Universal system benefits programs" means public purpose programs for:
     (a) cost-effective local energy conservation;
     (b) low-income customer weatherization;
     (c) renewable resource projects and applications, including those that capture unique social and energy system benefits or provide transmission and distribution system benefits;
     (d) research and development programs related to energy conservation and renewables;
     (e) market transformation designed to encourage competitive markets for public purpose programs; and
     (f) low-income energy assistance.
     (29) "Utility" means any public utility or cooperative utility.

     History: En. Sec. 3, Ch. 505, L. 1997.