 
     85-15-212.  Operating permit. (1) An operation plan must be prepared by the owner and approved by the department prior to operation of the high-hazard dam or reservoir. The operation plan must set forth at a minimum:
     (a)  a reservoir operation procedure;
     (b)  a maintenance procedure for the high-hazard dam and appurtenant works; and
     (c)  emergency procedures and warning plans.
     (2)  When construction is complete and if the high-hazard dam or reservoir conforms to the construction permit and when an operation plan has been approved, the department shall issue a permit to operate the high-hazard dam or reservoir, containing conditions on the safe operation of the high-hazard dam as it considers necessary. 
     History: En. Sec. 9, Ch. 501, L. 1985; amd. Sec. 5, Ch. 418, L. 1993. 
 


 
