     19-3-2131. (Temporary) Implementation schedule -- plan effective date. (1) In exercising its authority pursuant to this part to implement the defined contribution plan, the board shall:
     (a) by September 1, 1999, retain a qualified consultant to assist the board in developing appropriate requests for proposals for contracted services;
     (b) by January 1, 2000, issue a request for proposal for all required contracted services;
     (c) by August 1, 2000, award the contracts for all required contracted services; and
     (d) by September 1, 2000, begin the development and modification of data systems and reporting processes required to administer the plan.
     (2) The defined contribution plan must become operational by no later than July 1, 2002. (Terminates July 1, 2002--sec. 81(2), Ch. 471, L. 1999.)

     History: En. Sec. 60, Ch. 471, L. 1999.