Montana Code Annotated 1999

MCA ContentsSearchPart Contents


     28-2-2103. Payment to contractor and subcontractor. (1) If a contractor performs a construction contract according to the terms of the contract and requests, either directly to the owner or to owner's representative, payment for performance of the contract, the owner shall pay the contractor, within 30 days after receipt by the owner or the owner's representative of the request for payment, for work performed or materials provided in accordance with the contract.
     (2) Within 3 working days after a contractor receives a periodic or final payment from an owner or a state agency, the contractor shall pay the subcontractor, if any, the full amount due the subcontractor in accordance with the subcontract for work performed or materials provided in accordance with that subcontract.
     (3) Within 3 working days after a subcontractor receives a periodic or final payment from a contractor, the subcontractor shall pay another subcontractor, if any, the full amount due the subcontractor under the subcontract for work performed or materials provided in accordance with that subcontract.

     History: En. Sec. 5, Ch. 470, L. 1999.

Previous SectionHelpNext Section
Provided by Montana Legislative Services