Montana Code Annotated 1999

MCA ContentsSearchPart Contents


     69-14-605. Time for completion of crossing. It shall be the duty of a railroad company to construct a crossing ordered by the board of county commissioners of any county within 60 days after service of such order; provided, however, that in case any crossing shall be ordered requiring any extended period of construction, such additional time as is reasonably necessary to complete the same shall be allowed by the commission upon the proper application for such extension.

     History: En. Sec. 4, Ch. 148, L. 1919; re-en. Sec. 6628, R.C.M. 1921; re-en. Sec. 6628, R.C.M. 1935; amd. Sec. 20, Ch. 315, L. 1974; R.C.M. 1947, 72-704.

Previous SectionHelpNext Section
Provided by Montana Legislative Services