Montana Code Annotated 1999

MCA ContentsSearchPart Contents


     85-7-1941. Contracts. (1) The construction by the district of irrigation works may be done by the district, by private owners, or by contract.
     (2) Before any contract is let, the board of commissioners shall provide surveys, plans, maps, and estimates, which shall include everything necessary to show the entire cost in detail of everything necessary to complete the work required to irrigate any of the lands in the district under the proposed system.
     (3) Notice of any contract to be awarded for the construction of such works shall state where the plans and specifications may be seen and shall be published at least once a week for 3 successive calendar weeks in a newspaper published or of general circulation in the county where the office of the district is located. Sealed bids shall be called for in such published notice, and bids shall be opened in public.

     History: En. Sec. 25, Ch. 146, L. 1909; amd. Sec. 4, Ch. 145, L. 1915; re-en. Sec. 7195, R.C.M. 1921; re-en. Sec. 7195, R.C.M. 1935; R.C.M. 1947, 89-1501(part); amd. Sec. 8, Ch. 112, L. 1981.

Previous SectionHelpNext Section
Provided by Montana Legislative Services