Montana Code Annotated 1999

MCA ContentsSearchPart Contents


     87-5-504. Notice of department findings and alternative plans. Within 30 days after the receipt of such plans, the department shall notify the applicant whether or not such construction project or hydraulic project will adversely affect any fish or game habitat. If the department notifies the applicant that such construction will adversely affect any fish or game habitat, it shall accompany such notice with recommendations or alternative plans which will eliminate or diminish such adverse effect.

     History: En. Sec. 4, Ch. 10, L. 1965; amd. Sec. 13, Ch. 417, L. 1977; R.C.M. 1947, 26-1504.

Previous SectionHelpNext Section
Provided by Montana Legislative Services