     18-2-422. Bid specification and public works contract to contain standard prevailing wage rate and payroll record notification. All public works contracts and the bid specifications for those contracts must contain:
     (1) a provision stating for each job classification the standard prevailing wage rate, including fringe benefits, that the contractors and employers shall pay during construction of the project;
     (2) a provision requiring each contractor and employer to maintain payroll records in a manner readily capable of being certified for submission under 18-2-423, for not less than 3 years after the contractor's or employer's completion of work on the project; and
     (3) a provision requiring each contractor to post a statement of all wages and fringe benefits in compliance with 18-2-423.

     History: En. Sec. 4, Ch. 139, L. 1981; amd. Sec. 5, Ch. 522, L. 1997; amd. Sec. 3, Ch. 517, L. 2001.