69-5-106. Electric service facilities to large customers. (1) An electric utility has the right to furnish electric service facilities to any premises if the estimated connected load for full operation at the premises will be 400 kilowatts or larger within 2 years from the date of initial service and if the electric utility can extend its facilities to the premises at less cost to the electric utility than the electric cooperative cost. The estimated connected load must be determined from the plans and specifications prepared for construction of the premises or, if an estimate is not available, must be determined by agreement of the electric facilities provider and the customer. The fact that the actual connected load after 2 years from the date of initial service is less than 400 kilowatts does not affect the right of the electric facilities provider initially providing electric service facilities to continue to provide electric service facilities to the premises.
(2) An independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine which electric facilities provider can extend its facilities at the least cost to the utility. The cost of those engineering services must be paid equally by the electric facilities providers involved.
History: En. Sec. 3, Ch. 7, L. 1971; R.C.M. 1947, 70-503(3); amd. Sec. 12, Ch. 43, L. 1979; amd. Sec. 38, Ch. 505, L. 1997.