85-2-316. State reservation of waters. (1) The state, any political subdivision or agency of the state, or the United States or any agency of the United States may apply to the department to acquire a state water reservation for existing or future beneficial uses or to maintain a minimum flow, level, or quality of water throughout the year or at periods or for a length of time that the department designates.
(2) (a) Water may be reserved for existing or future beneficial uses in the basin where it is reserved, as described by the following basins:
(i) the Clark Fork River and its tributaries to its confluence with Lake Pend Oreille in Idaho;
(ii) the Kootenai River and its tributaries to its confluence with Kootenay Lake in British Columbia;
(iii) the St. Mary River and its tributaries to its confluence with the Oldman River in Alberta;
(iv) the Little Missouri River and its tributaries to its confluence with Lake Sakakawea in North Dakota;
(v) the Missouri River and its tributaries to its confluence with the Yellowstone River in North Dakota; and
(vi) the Yellowstone River and its tributaries to its confluence with the Missouri River in North Dakota.
(b) A state water reservation may be made for an existing or future beneficial use outside the basin where the diversion occurs only if stored water is not reasonably available for water leasing under 85-2-141 and the proposed use would occur in a basin designated in subsection (2)(a).
(3) Upon receiving a correct and complete application, the department shall proceed in accordance with 85-2-307 through 85-2-309. After the hearing provided for in 85-2-309, the department shall decide whether to reserve the water for the applicant. The department's costs of giving notice, holding the hearing, conducting investigations, and making records incurred in acting upon the application to reserve water, except the cost of salaries of the department's personnel, must be paid by the applicant. In addition, a reasonable proportion of the department's cost of preparing an environmental impact statement must be paid by the applicant unless waived by the department upon a showing of good cause by the applicant.
(4) (a) The department may not adopt an order reserving water unless the applicant establishes to the satisfaction of the department by a preponderance of evidence:
(i) the purpose of the reservation;
(ii) the need for the reservation;
(iii) the amount of water necessary for the purpose of the reservation;
(iv) that the reservation is in the public interest.
(b) In determining the public interest under subsection (4)(a)(iv), the department may not adopt an order reserving water for withdrawal and transport for use outside the state unless the applicant proves by clear and convincing evidence that:
(i) the proposed out-of-state use of water is not contrary to water conservation in Montana; and
(ii) the proposed out-of-state use of water is not otherwise detrimental to the public welfare of the citizens of Montana.
(c) In determining whether the applicant has proved by clear and convincing evidence that the requirements of subsections (4)(b)(i) and (4)(b)(ii) are met, the department shall consider the following factors:
(i) whether there are present or projected water shortages within the state of Montana;
(ii) whether the water that is the subject of the application could feasibly be transported to alleviate water shortages within the state of Montana;
(iii) the supply and sources of water available to the applicant in the state where the applicant intends to use the water; and
(iv) the demands placed on the applicant's supply in the state where the applicant intends to use the water.
(d) When applying for a state water reservation to withdraw and transport water for use outside the state, the applicant shall submit to and comply with the laws of the state of Montana governing the appropriation, lease, use, and reservation of water.
(5) If the purpose of the state water reservation requires construction of a storage or diversion facility, the applicant shall establish to the satisfaction of the department by a preponderance of evidence that there will be progress toward completion of the facility and accomplishment of the purpose with reasonable diligence in accordance with an established plan.
(6) The department shall limit any state water reservations after May 9, 1979, for maintenance of minimum flow, level, or quality of water that it awards at any point on a stream or river to a maximum of 50% of the average annual flow of record on gauged streams. Ungauged streams may be allocated at the discretion of the department.
(7) After the adoption of an order reserving waters, the department may reject an application and refuse a permit for the appropriation of reserved waters or may issue the permit subject to terms and conditions that it considers necessary for the protection of the objectives of the reservation.
(8) (a) A person desiring to use water reserved to a conservation district for agricultural purposes shall make application for the use with the district, and the district, upon approval of the application, shall inform the department of the approved use and issue the applicant an authorization for the use. The department shall maintain records of all uses of water reserved to conservation districts and be responsible, when requested by the districts, for rendering technical and administrative assistance within the department's staffing and budgeting limitations in the preparation and processing of the applications for the conservation districts. The department shall, within its staffing and budgeting limitations, complete any feasibility study requested by the districts within 12 months of the time that the request was made. The department shall extend the time allowed to develop a plan identifying projects for using a district's reservation as long as the conservation district makes a good faith effort, within its staffing and budget limitations, to develop a plan.
(b) Upon actual application of water to the proposed beneficial use, the authorized user shall notify the conservation district. The notification must contain a certified statement by a person with experience in the design, construction, or operation of project works for agricultural purposes describing how the reserved water was put to use. The department or the district may then inspect the appropriation to determine if it has been completed in substantial accordance with the authorization.
(9) Except as provided in 85-2-331, the priority of appropriation of a state water reservation and the relative priority of the reservation to permits with a later priority of appropriation must be determined according to this subsection (9), as follows:
(a) A state water reservation under this section has a priority of appropriation dating from the filing with the department of a notice of intention to apply for a state water reservation in a basin in which no other notice of intention to apply is currently pending. The notice of intention to apply must specify the basin in which the applicant is seeking a state water reservation.
(b) Upon receiving a notice of intention to apply for a state water reservation, the department shall identify all potential state water reservation applicants in the basin specified in the notice and notify each potential applicant of the opportunity to submit an application and to receive a state water reservation with the priority of appropriation as described in subsection (9)(a).
(c) To receive the priority of appropriation described in subsection (9)(a), the applicant shall submit a correct and complete state water reservation application within 1 year after the filing of the notice of intention to apply. Upon a showing of good cause, the department may extend the time for preparing the application.
(d) The department may by order subordinate a state water reservation to a permit or a certificate for ground water development issued pursuant to this part if:
(i) the permit application or the notice of completion of ground water development was accepted by the department before the date of the order granting the reservation;
(ii) the effect of subordinating the reservation to one or more permits or certificates for ground water development does not interfere substantially with the purpose of the reservation; and
(iii) in the case of a certificate for ground water development, the reservant consents to the subordination.
(e) The department shall by order establish the relative priority of state water reservations approved under this section that have the same day of priority. A state water reservation may not adversely affect any rights in existence at that time.
(10) The department shall, periodically but at least once every 10 years, review existing state water reservations to ensure that the objectives of the reservations are being met. When the objectives of a state water reservation are not being met, the department may extend, revoke, or modify the reservation. Any undeveloped water made available as a result of a revocation or modification under this subsection is available for appropriation by others pursuant to this part.
(11) The department may modify an existing or future order originally adopted to reserve water for the purpose of maintaining minimum flow, level, or quality of water, so as to reallocate the state water reservation or portion of the reservation to an applicant who is a qualified reservant under this section. Reallocation of water reserved pursuant to a state water reservation may be made by the department following notice and hearing if the department finds that all or part of the reservation is not required for its purpose and that the need for the reallocation has been shown by the applicant to outweigh the need shown by the original reservant. Reallocation of reserved water may not adversely affect the priority date of the reservation, and the reservation retains its priority date despite reallocation to a different entity for a different use. The department may not reallocate water reserved under this section on any stream or river more frequently than once every 5 years.
(12) A reservant may not make a change in a state water reservation under this section, except as permitted under 85-2-402 and this subsection. If the department approves a change, the department shall give notice and require the reservant to establish that the criteria in subsection (4) will be met under the approved change.
(13) A state water reservation may be transferred to another entity qualified to hold a reservation under subsection (1). Only the entity holding the reservation may initiate a transfer. The transfer occurs upon the filing of a water right transfer certificate with the department, together with an affidavit from the entity receiving the reservation establishing that the entity is a qualified reservant under subsection (1), that the entity agrees to comply with the requirements of this section and the conditions of the reservation, and that the entity can meet the objectives of the reservation as granted. If the transfer of a state water reservation involves a change in an appropriation right, the necessary approvals must be acquired pursuant to subsection (12).
(14) This section does not vest the department with the authority to alter a water right that is not a state water reservation.
(15) The department shall undertake a program to educate the public, other state agencies, and political subdivisions of the state as to the benefits of the state water reservation process and the procedures to be followed to secure the reservation of water. The department shall provide technical assistance to other state agencies and political subdivisions in applying for reservations under this section.
(16) Water reserved under this section is not subject to the state water leasing program established under 85-2-141.
History: En. Sec. 26, Ch. 452, L. 1973; amd. Sec. 11, Ch. 485, L. 1975; amd. Sec. 7, Ch. 416, L. 1977; R.C.M. 1947, 89-890; amd. Sec. 1, Ch. 689, L. 1979; amd. Sec. 1, Ch. 186, L. 1981; amd. Sec. 6, Ch. 357, L. 1981; amd. Sec. 15, Ch. 573, L. 1985; amd. Sec. 1, Ch. 197, L. 1987; amd. Sec. 1, Ch. 389, L. 1989; amd. Sec. 1, Ch. 515, L. 1991; amd. Sec. 6, Ch. 370, L. 1993; amd. Sec. 449, Ch. 418, L. 1995; amd. Sec. 1, Ch. 330, L. 1997; amd. Sec. 9, Ch. 497, L. 1997.