69-8-420. Electricity supply resource procurement plans -- comment on plans. (1) The public utility shall develop electricity supply resource procurement plans. The plans must be submitted to the commission at intervals determined in rules adopted by the commission.
(2) An electricity supply resource procurement plan must demonstrate the public utility's achievement of the objectives provided in 69-8-419 and compliance with commission rules.
(3) The commission shall:
(a) review the electricity supply resource procurement plan;
(b) provide an opportunity to the public to comment on the plan; and
(c) issue written comments that identify:
(i) any concerns of the commission regarding the public utility's compliance with commission rules; and
(ii) ways to remedy any concerns.