TITLE 75. ENVIRONMENTAL PROTECTION

CHAPTER 20. MAJOR FACILITY SITING

Part 3. Decisions

Conditions Imposed

75-20-302. Conditions imposed. (1) If the department determines that the location of all or a part of the proposed facility should be modified, it may condition its certificate upon the modification, provided that the persons residing in the area affected by the modification have been given reasonable notice of the modification.

(2) The department may require the applicant to post performance bonds to guarantee successful reclamation and revegetation of the project area.

History: En. Sec. 10, Ch. 327, L. 1973; amd. Sec. 10, Ch. 494, L. 1975; R.C.M. 1947, 70-810(2); amd. Sec. 16, Ch. 676, L. 1979; amd. Sec. 1, Ch. 155, L. 1985; amd. Sec. 228, Ch. 418, L. 1995; amd. Sec. 541, Ch. 546, L. 1995; amd. Sec. 16, Ch. 329, L. 1997.