28-2-723. Construction contracts requiring lien or bond waiver void, MCA

Montana Code Annotated 2017

TITLE 28. CONTRACTS AND OTHER OBLIGATIONS

CHAPTER 2. CONTRACTS

Part 7. Illegal Objects and Provisions

Construction Contracts Requiring Lien Or Bond Waiver Void

28-2-723. Construction contracts requiring lien or bond waiver void. A construction contract may not contain provisions requiring a contractor, subcontractor, or material supplier to waive the right to a construction lien or a right to a claim against a payment bond before the contractor, subcontractor, or material supplier has been paid for the labor, materials, or both labor and materials, furnished by the contractor, subcontractor, or material supplier.

History: En. Sec. 1, Ch. 119, L. 1999.