Priority

71-3-904. Priority. The lien for labor or services performed or material furnished as specified in this part shall be prior to and have precedence over any mortgage, encumbrance, or other lien upon said grain or crops, except the lien for seed, hail insurance, threshing, labor, and warehouse services furnished for the purpose of growing or handling the particular grain or crops.

History: En. Sec. 4, Ch. 205, L. 1953; R.C.M. 1947, 45-1404.