75-11-312. Review of corrective action plans and claims, MCA

Montana Code Annotated 2017

TITLE 75. ENVIRONMENTAL PROTECTION

CHAPTER 11. UNDERGROUND STORAGE TANKS

Part 3. Petroleum Storage Tank Cleanup

Review Of Corrective Action Plans And Claims

75-11-312. Review of corrective action plans and claims. (1) To ensure that the fund provided for in 75-11-313 is being used in the most efficient manner, the board may implement a program of third-party review for corrective action plans and claims. The board may submit a corrective action plan or claim for review by a qualified third party of the board's choosing.

(2) If a third-party review suggests that a corrective action plan is inappropriate for the release, the board may remand the plan to the department for further review.

(3) If a third-party review suggests that submitted costs do not comply with the requirements of 75-11-309(3)(a), the board may deny the costs, subject to 75-11-309(4).

History: En. Sec. 4, Ch. 245, L. 2003; amd. Sec. 4, Ch. 356, L. 2005.