18-2-422. Bid specification and public works contract to contain standard prevailing wage rate and payroll record notification, MCA

Montana Code Annotated 2019

TITLE 18. PUBLIC CONTRACTS

CHAPTER 2. CONSTRUCTION CONTRACTS

Part 4. Special Conditions -- Standard Prevailing Rate of Wages

Bid Specification And Public Works Contract To Contain Standard Prevailing Wage Rate And Payroll Record Notification

18-2-422. Bid specification and public works contract to contain standard prevailing wage rate and payroll record notification. All public works contracts and the bid specifications for those contracts must contain:

(1) a provision stating for each job classification the standard prevailing wage rate, including fringe benefits, that the contractors and employers shall pay during construction of the project;

(2) a provision requiring each contractor and employer to maintain payroll records in a manner readily capable of being certified for submission under 18-2-423, for not less than 3 years after the contractor's or employer's completion of work on the project; and

(3) a provision requiring each contractor to post a statement of all wages and fringe benefits in compliance with 18-2-423.

History: En. Sec. 4, Ch. 139, L. 1981; amd. Sec. 5, Ch. 522, L. 1997; amd. Sec. 3, Ch. 517, L. 2001.