71-3-1203. Enforcement of lien -- sale. If payment for work, labor, or services performed or feed or material furnished is not made within 30 days after the performance of the work, labor, or services or furnishing of the feed or material, the lienor under the provisions of this part may enforce the lien in the following manner:
(1) The lienor may file a lien enforcement action in a court of competent jurisdiction in the county in which the:
(a) contract between the lienor and the owner of the property was entered into;
(b) owner resided at the time the lien enforcement action commenced; or
(c) property is located.
(2) Issuance or service of a summons is not required when a claim is made under this section. The order to show cause pursuant to subsection (5)(a) is in lieu of a summons as permitted by Rule 4(c)(2)(C), M.R.Civ.P., and Rule 4D(3) of the Montana Justice and City Courts Rules of Civil Procedure. A notice to or service of process on the owner is not required prior to the issuance of the order to show cause pursuant to subsection (5)(a).
(3) When a claim is made under this section for a lien other than a nonpossessory special lien, an affidavit must be made by the lienor claiming the property or by someone on the lienor's behalf, stating:
(a) the facts that the lienor performed a service for the property owner entitling the lienor to a lien on the owner's property pursuant to 71-3-1201;
(b) that the service described in subsection (3)(a) was performed at the written or verbal request of the owner or owner's agent;
(c) the particular property upon which the lien is claimed; and
(d) an itemized list of the charges that are due and unpaid under the lien.
(4) When a claim is made under this section for a nonpossessory special lien, the lienor shall submit to the court:
(a) a copy of the document required by 71-3-1201(2)(c); and
(b) a statement of the charges that are due and unpaid under the lien.
(5) (a) If satisfactory, the court shall order the owner of the property to show cause why the property should not be sold pursuant to the procedures in this section. The order must include the date and time for a hearing.
(b) One copy of the order to show cause provided for in subsection (5)(a) must be served on the owner by certified mail, return receipt requested, and one copy must be served by first-class mail at the owner's last address known to the lienor at least 21 days before the hearing date.
(6) The lienor shall deliver to the sheriff of the county in which the property is located a copy of the court's lien enforcement judgment.
(7) Upon receipt of the court's lien enforcement judgment, the sheriff shall advertise and sell at public auction as much of the property covered by the lien as will satisfy the lien.
(8) The sale must be advertised, conducted, and held in the same manner as prescribed in 25-13-701(1)(b).
(9) The owner of the property may request a hearing in a court of competent jurisdiction to contest any matter regarding the sale of the property.
(10) The sheriff shall apply the proceeds of the sale to the discharge of the lien and the cost of the proceedings in selling the property and enforcing the lien, and the remainder, if any, or a part that is required to discharge the claims, must be turned over by the sheriff to the holders, in the order of their precedence, of the chattel mortgages or other lien claimants of record against the property, and the balance of the proceeds must be turned over to the owner of the property.